Cleanup and Closure Milestones at SRS
James A. Rispoli, DOE Assistant Secretary
for Environmental Management (EM) paid a visit to the Savannah
River Site June 19 to mark the start of normal operations
of interim salt waste processing facilities - the Actinide
Removal Process (ARP) and the Modular Caustic Side Solvent
Extraction Unit (MCU) - and the official closure of the General
Separations Area Consolidated Unit (GSACU). Removing
the salt waste, which fills approximately 90 percent of the
tank space in the SRS tank farms, is a major step toward closing
the Site’s 49 high-level waste tanks that currently
contain about 36 million gallons of waste.
“The Savannah River Site has successfully achieved a
first-of-a-kind capability to process Cold War era salt waste
out of the waste storage tanks,” said Rispoli.
“The successful startup and operations of innovative
projects such as ARP and MCU demonstrate the real progress
SRS is making to safely clean up and protect the environment
while clearing the way for future DOE missions.”
ARP and MCU together make up the Interim Salt Disposition
Processing system, which decontaminates radioactive salt waste
from SRS’s waste storage tanks to be safely dispositioned.
SRS first received radioactive salt waste solution for processing
at the ARP and MCU facilities in April 2008 and completed
a successful shake-down run as the facilities were brought
online in a deliberate, sequenced process to ensure safe operations.
In combination with the Saltstone Production and Disposal
Facilities, this innovative approach can treat, decontaminate,
and disposition radioactive salt waste removed from SRS storage
tanks.
“Beginning normal operations for the entire ARP/MCU
system is a significant accomplishment made possible through
the teamwork of the Department, state regulators, and our
Site contractor,” said DOE-SRManager Jeffrey Allison.
“Ushering in a new era of salt waste processing supports
DOE’s highest priority to close waste tanks and demonstrates
that SRS is solving critical cleanup challenges with smart
solutions.”
Assistant Secretary Rispoli also recognized the official closure
of the General Separations Area Consolidated Unit (GSACU),
which consisted of four waste units covering 76-acres that
contained more than seven million cubic feet of solid low-level
radioactive wastes. The GSACU has been safely remediated
and contained under a state-of-the-art geosynthetic cap designed
to protect the environment for hundreds of years. The
remediation work was finished in April 2007, and the unit
was declared closed in November 2007. The final paperwork
was transferred in June 2008. The project was safely
completed eight months ahead of schedule and under budget
at a cost of $56 million - well under the $75 million estimate.
Located near the center of SRS, the Old Radioactive Waste
Burial Ground (ORWBG) served as the Site’s main burial
ground for 22 years. Over 7 million cubic feet of solid
low-level radioactive wastes are buried at the ORWBG, including
contaminated substances from other DOE and Department of Defense
sites. The area was filled in 1974 and in 1996, DOE
issued an Interim Record of Decision to place a low-permeability
soil cover over the ORWBG, which was complete in 1998.
In 2001, work began on the final remedy. First, 22 underground
solvent tanks, each with a capacity of about 25,000 gallons,
were filled with grout to stabilize the contamination, eliminate
voids, and provide structural stability. Once the tanks
were grouted and closed, several buildings, including a Resource
Conservation and Recovery Act (RCRA)-permitted building that
required a RCRA closure, were removed. These buildings
housed employees and were used to ship transuranic waste to
DOE’s Waste Isolation Pilot Plant facility in New Mexico.
Next, about 5,000 to 25,000 cubic yards of waste were removed
from waste units that had been used as emergency basins for
releases and the units were dug up and transported to the
ORWBG. Finally, the final 76-acre cap was installed.
FACT
SHEETS I MEDIA CONTACTS
I NEWS RELEASES I WSRC
NEWS
PHOTOGRAPHS I SPEAKERS I NEWS & EVENTS
HOME
|